Scheduled task can not be done because date format is wrong in BMS

Publication Date:  2012-07-24 Views:  52 Downloads:  0
Issue Description
BMS version:  V200R011C01B037
Scheduled task can not be done.
Alarm Information
Null
Handling Process
Set the date as following to try:
File--->System Settings 
change the date format to yyyy-MM-dd, then check a task to check this problem.
The problem has been solved.
Root Cause
See attachment:
Double click the task, appear the New task page, and we see the Execute date format is YYYY-MM-DD, but the actuall date format we configure is DD-MM-YYYY. Problem root cause should be this.
Suggestions
Null

END