FAQ- How to replace Cross-Connect Boards

Publication Date:  2012-07-25 Views:  31 Downloads:  0
Issue Description
Sometimes  the existing networks  are facing an issue of cross-connect capacity upgrade,in the normal situation for example :
From SSN1GXCSA to SSN1EXCSA
From SSN1GXCSA to SSN1UXCSA
From SSN1GXCSA to SSN1UXCSB
From SSN1EXCSA to SSN1UXCSA
From SSN1EXCSA to SSN1UXCSB
From SSN1UXCSA to SSN1UXCSB
From SSN1GXCSA to SSN1SXCSA
From SSN1GXCSA to SSN1SXCSB
From SSN1EXCSA to SSN1SXCSA
From SSN1EXCSA to SSN1SXCSB
From SSN1UXCSA to SSN1SXCSA
From SSN1UXCSA to SSN1SXCSB
From SSN1UXCSB to SSN1SXCSB
From SSN1SXCSA to SSN1SXCSB
From SSN1GXCSA to SSN1IXCSA;
From SSN1GXCSA to SSN1IXCSB; 
From SSN1EXCSA to SSN1IXCSA;
From SSN1EXCSA to SSN1IXCSB; 
From SSN1IXCSA to SSN1IXCSB;
From SSN1UXCSA to SSN1IXCSA;
From SSN1UXCSA to SSN1IXCSB
From SSN1UXCSB to SSN1IXCSB;
From SSN1SXCSA to SSN1IXCSA
From SSN1SXCSA to SSN1IXCSB
From SSN1SXCSB to SSN1IXCSB
we can upgarde the Cross-Connect Boards   according to <<OptiX OSN3500&7500 Cross-Connect Boards Replacing Guide>> ,the Cross-Connect Boards  can be repalced smoothly without serveice interruption,but in some special situation for example :
From SSN1UXCSB to SSN1SXCSA
From SSN1SXCSB to SSN1IXCSA
we cann't replace the Cross-Connect Boards  smoothly ,because the Nesoft doesn't support . This case shows a way for your reference.
Alarm Information
null
Handling Process
Now there is a method to resolve this question :
1. In NE physically replace standby  SXCSB to IXCSA board
2. In NMS (U2000 or T2000) set pre-configure mode for this OSN3500.
3. In NMS delete both logical SXCSB,  create two IXCSA
4. In NMS delete pre-configure mode, download the configuration to the NE  in non-interrupt mode.
5. In NE physically replace another SXCSB to IXCSA board
6. Wait for HSC_UNAVAIL alarm finish, make switching test.
Be careful, in this situation  the service will be interrupted during configuration checkout, so engineer must apply interruption time .
Root Cause
null
Suggestions
null

END