NetCol5000C-35kW and NetCol5000-11kW-software adjustment

Publication Date:  2018-01-30 Views:  70 Downloads:  0
Issue Description

During the Load Bank Testing and Power Tests for NetCol5000C-35 kW and NetCol5000C-11kW inside of the FusionModule2000 and FusionModule800, when the customer simulated the Power failure , the NetCol5000 went down , but when Mains come back again , for the NetCol5000 it took 2-5 minutes to load the software and start to cool down the FM2000 and FM800.

We suggest: 1) to keep plug in/power on  the MainBoard of the NetCol5000 with the UPS, in order not to take so much time for the NetCol to start cooling.

                   2) minimize software start time from 2-5 minutes to 30 seconds

                   3) install additional battery for NetCol5000C -mainboard in order to be always power on

 

 

The NetCol5000C is taking 2-5 minutes till the software will load and the NetCol5000C will start running , so long time.

 

Solution

In case of power failure the NetCol5000C-35kW and NetCol5000C- 11kW  are going down because are connected to Main Line  

 

We suggest: 1) to keep plug in/power on  the MainBoard of the NetCol5000 with the UPS, in order not to take so much time for the NetCol to start cooling.

                   2) minimize software start time from 2-5 minutes to 30 seconds

                   3) install additional battery for NetCol5000C -mainboard in order to be always power on

 

 