About This Document
Purpose
This document describes the planning before the installation of mission-critical storage systems, including the planning for the networks, installation environment, and data. The following table lists the product models to which this document applies:
Product Series |
Product Model |
---|---|
OceanStor 18000 V3 series |
OceanStor 18500 V3 and 18800 V3 |
OceanStor 18000F V3 series |
OceanStor 18500F V3 and 18800F V3 |
Intended Audience
This document is intended for:
- Technical support engineers
- Maintenance engineers
Symbol Conventions
The symbols that may be found in this document are defined as follows.
Symbol |
Description |
---|---|
Indicates an imminently hazardous situation which, if not avoided, will result in death or serious injury. |
|
Indicates a potentially hazardous situation which, if not avoided, could result in death or serious injury. |
|
Indicates a potentially hazardous situation which, if not avoided, may result in minor or moderate injury. |
|
Indicates a potentially hazardous situation which, if not avoided, could result in equipment damage, data loss, performance deterioration, or unanticipated results. NOTICE is used to address practices not related to personal injury. |
|
Calls attention to important information, best practices and tips. NOTE is used to address information not related to personal injury, equipment damage, and environment deterioration. |
Change History
Changes between document issues are cumulative. The latest document issue contains all the changes made in earlier issues.
Issue 09 (2019-01-25)
This issue is the ninth official release.
Optimized some descriptions.
Issue 08 (2018-12-06)
This issue is the eighth official release.
Made some changes in specifications.
Issue 07 (2018-07-30)
This issue is the seventh official release.
Made some changes in specifications.
Issue 06 (2018-05-09)
This issue is the sixth official release.
Made some changes in specifications.
Issue 05 (2018-01-30)
This issue is the fifth official release.
Made some changes in specifications.
Issue 04 (2017-11-30)
This issue is the fourth official release.
Optimized related descriptions.
Added the Collecting Live Network Information section.
Issue 03 (2017-08-30)
This issue is the third official release.
Added introduction of high voltage DC.
Issue 02 (2017-06-01)
This issue is the second official release.
Made minor changes in specifications.
Issue 01 (2017-02-28)
This issue is the first official release.