CX116 Pass-Through Module V100R001 User Guide 16

This document describes the CX116 gigabit Ethernet (GE) pass through module of the Tecal E9000 server (short for E9000) in terms of its features, installation, removal, and maintenance.
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Removing the CX116

Removing the CX116

Scenarios

This topic describes a recommended process for removing the CX116 from the E9000 chassis. Get familiar with hardware devices before any operation.

To replace a CX116, see section "Replacing a Switch Module" in the E9000 Server V100R001 User Guide.

Prerequisites

Tools

The following tools must be obtained for removing the CX116:

  • Electrostatic discharge (ESD) gloves
  • ESD bag
  • Phillips screwdriver (PH3 is 8 mm or 0.31 in.)

Workflow

Figure 3-7 Removal process

Procedure

  1. Removerd the CX116 network cables.
  2. Determine the slot of the CX116 to be removed.

    Figure 3-8 Slot numbers

  3. Remove the CX116.

    1. Use a Phillips screwdriver to loosen the two M3 captive screws on the CX116. See step (1) in Figure 3-9.
      Figure 3-9 Removing the CX116
    2. Raise the two ejector levers on the CX116 completely. See steps (2) in Figure 3-9.
    3. Pull the CX116 out of the chassis horizontally. See steps and (3) in Figure 3-9.
    4. Lower the ejector levers on the CX116 completely. See step (4) in Figure 3-9.
      NOTICE:

      An ESD bag can hold only one CX116.

    5. Place the removed CX116 in an ESD bag.

  4. Install a filler panel.

    1. Raise the two ejector levers of the filler panel completely. See step (1) in Figure 3-10.
      Figure 3-10 Installing a filler panel
    2. Insert a filler panel into the chassis horizontally. See step (2) in Figure 3-10.
    3. Lower the two ejector levers of the filler panel completely. See step (3) in Figure 3-10.
    4. Use a Phillips screwdriver to tighten the two M3 captive screws on the filler panel. See step (4) in Figure 3-10.

Translation
Download
Updated: 2018-09-20

Document ID: EDOC1000015889

Views: 11942

Downloads: 487

Average rating:
This Document Applies to these Products
Related Documents
Related Version
Share
Previous Next