E9000 Server V100R001 User Guide 24

This document describes the overview, functions, structure, installation, and configuration methods of the E9000.
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installation Requirements for the PGND Cable and Power Cables

Installation Requirements for the PGND Cable and Power Cables

  • When routing PGND cable and power cables, measure the exact distance between the cabinet ground terminal and the ground bar and also the distance between the PDU connector and the AC PDC. Use cables with the proper length. If the cables are not long enough, replace the cables.
  • Trim off the excess length of the cabinet PGND cable and power cables. Do not coil up cables.
  • Connect the PGND cable of the E9000 chassis to the nearest ground terminal of the cabinet for an attractive layout. Coil the PGND cable if the excess length is long.
  • To improve system reliability and facilitate maintenance, connect the power cables of the E9000 chassis to different PDUs.
  • (Optional) Distinguish power cables installed on different PDUs by color.
Translation
Download
Updated: 2019-08-30

Document ID: EDOC1000015897

Views: 95842

Downloads: 5268

Average rating:
This Document Applies to these Products
Related Documents
Related Version
Share
Previous Next