RH5885 V3 Server V100R003 User Guide 32

This document describes the appearance, specifications, parameters, and structure of the RH5885 V3, and how to install an OS, replace parts, and install, remove, configure, and troubleshoot the server.
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Powering On

Powering On

Scenarios

Power on the server after it is installed properly or maintained.

Prerequisites

Conditions

The server and internal components are properly installed.

Data

  • You have determined the cabinet number and installation position for the device to be powered on.
  • You have obtained the IP address, user name, and user password for the management network port on the iMana 200.

Tools

ESD wrist strap or ESD gloves: used to prevent ESD damage

Documents

For details about how to obtain the IP address for the management network port and how to operate the iMana 200, see the Huawei Server iMana 200 User Guide.

Procedure

The power supply units (PSUs) are properly installed but not powered on.

Connect the external power supply to the PSUs. Then the server will be powered on along with the PSUs.

The PSUs are powered on, and the server is in the standby state.

  • Press and hold down the power button on the front panel until the server is powered on.
  • Remotely power on the server using the iMana 200 WebUI.

    Log in to the iMana 200 WebUI, choose PS Management > Power Control, and click Power On and then OK.

  • Remotely power on the server using the iMana 200 CLI.

    Run the ipmcset -d powerstate -v 1 command on the iMana 200 CLI.

Verification

Check the indicator status after the server is powered on.

Translation
Download
Updated: 2019-10-21

Document ID: EDOC1000040297

Views: 106258

Downloads: 1582

Average rating:
This Document Applies to these Products
Related Version
Related Documents
Share
Previous Next