X6800 Server V100R003 User Guide 13

This document describes the Huawei X6800 server (X6000 for short) in terms of its appearance, features, specifications, system components, device installation, cable connections, and installation verification.
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Replacing the Management Module

Replacing the Management Module

This section describes how to replace a management module.

Scenario

A management module is faulty.

Impact on the System

After the management module is removed, the health status indicator will blink red and the fans will run at full speed, which is normal.

Prerequisites

  1. Matters for Attention

    Install a new management module within 2 minutes after the management module is removed.

  2. Spare parts

    Obtain the spare management module and packing materials, for example, an ESD bag. Place them less than 0.5 m (1.64 ft) away from the cabinet.

  3. Data

    Cabinet number, chassis number, and slot number of the management module to be replaced.

    Locate the management module to be replaced based on the preceding information, and label its panel for identification.

    Back up the service data on the management module to be replaced.

  4. Tools

    ESD wrist strap or ESD gloves

Procedure

  1. Wear an ESD wrist strap or ESD gloves.
  2. Loosen the captive screws on the management module. See step (1) in Figure 5-5.
  3. Hold the handle and pull the management module gently out of the shelf. See step (2) in Figure 5-5.

    Figure 5-5 Removing a management module

  4. Place the removed management module into an ESD bag.
  5. Take a spare management module out of an ESD bag.
  6. Insert the management module horizontally into the slot until the management module snaps into the chassis. See step (1) in Figure 5-6.
  7. Tighten the captive screws on the management module. See step (2) in Figure 5-6.

    Figure 5-6 Installing a management module

Follow-up Procedure

  1. Power on the chassis. The management module is operating properly if its status indicator is steady green.
  2. Configure service data for the newly-installed management module.
Translation
Download
Updated: 2018-09-06

Document ID: EDOC1000066339

Views: 37844

Downloads: 1718

Average rating:
This Document Applies to these Products
Related Documents
Related Version
Share
Previous Next