CX710 Switch Module V100R001 User Guide 12

This document describes the CX710 40GE converged switch module of the E9000 server in terms of its features, installation, removal, and configuration.

Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Removing the CX710

Removing the CX710

This topic describes how to remove the CX710 from the E9000 chassis.

Scenarios

Remove the CX710 from the E9000 chassis. Before the operation, become familiar with the hardware devices.

To replace a switch module, see section "Replacing a Switch Module" in the E9000 Server V100R001 User Guide.

Impact on the System

After the switch module is removed, all services running on the switch module stop.

Prerequisites

Tools

The following tools are available:

  • Protective gloves
  • Electrostatic discharge (ESD) gloves
  • Phillips screwdriver (PH2 is 6 mm or 0.25 in.)

Workflow

Figure 3-9 Removal process

Procedure

  1. Determine the CX710 to be removed.

    Figure 3-10 Slot numbers

  2. Determine the connection relationships between signal cables and ports on the CX710.

    Figure 3-11 Port types and numbers

    1

    BMC serial port

    2

    SYS serial port

    3

    40GE optical port

    -

    -

  3. (Optional) Remove a serial cable.

    Figure 3-12 Removing a serial cable

    The BMC serial port, SYS serial port, are standard RJ-45 ports and are disconnected in the same way.

  4. Remove an optical fiber and optical module.

    1. Determine the optical module type and removal position based on site requirements.
    2. Remove the optical module horizontally from the optical port. See (1) in Figure 3-13.
      Figure 3-13 Removing an optical module and optical fiber
    3. Remove the optical fiber from the optical module. See (2) and (3) in Figure 3-13.
    4. Install dust-proof caps for the optical module, as shown in Figure 3-14.
      Figure 3-14 Installing dust-proof caps

  5. Remove the CX710.

    1. Use a Phillips screwdriver to loosen the two M3 captive screws. See (1) in Figure 3-15.
      Figure 3-15 Removing the switch module
    2. Raise the two ejector levers on the CX710 completely and pull the switch module horizontally out of the chassis. See (2) and (3) in Figure 3-15.
    3. Lower the ejector levers on the CX710. See (4) in Figure 3-15.

      An ESD bag holds only one switch module.

    4. Place the removed switch module into an ESD bag.

  6. Install a switch module filler panel.

    1. Raise the two handles on the switch module filler panel and push the filler panel horizontally into the chassis as far as it will go. See (1) in Figure 3-16.
      Figure 3-16 Installing a switch module filler panel
    2. Lower the two handles on the switch module filler panel. See (2) in Figure 3-16.
    3. Use a Phillips screwdriver to tighten the two M3 captive screws on the switch module filler panel. See (3) in Figure 3-16.

Translation
Download
Updated: 2019-12-04

Document ID: EDOC1000069172

Views: 31964

Downloads: 463

Average rating:
This Document Applies to these Products

Related Version

Related Documents

Share
Previous Next