Installing S9310 and S9310X Chassis
Prerequisites
- Do not block the air intake vent (on the left side) and air exhaust vent (at the rear) on the chassis. Leave 70 mm to 90 mm clearance to ensure effective heat dissipation.
- Do not move or lift a switch by the top edges of the chassis as this may distort the chassis.
- When installing a switch, ensure that the chassis bottom is completely attached to the guide rails or tray in the cabinet or rack.
- If a fully configured chassis is delivered, remove cards and power modules before the installation. Install them after the chassis is installed.
Keep the tweezers delivered with the switch for future use.
Tools and Accessories
- Scissors
- Flat-head screwdriver
- Phillips screwdriver
- Marker
- Installation template
- Floating nuts and matching screws
- Guide rails and matching screws (separately purchased)
- Removable handles
Procedure
- Install mounting brackets. Measure the distance a from the front mounting rails to the interior side of the front door (see Checking the Cabinet or Rack), and then install mounting brackets to the switch based on the mapping between distance a and mounting bracket installation positions.Table 7-4 Mapping between distance a and mounting bracket installation positions
Mounting Bracket Installation Position
68 mm
See Figure 7-24.
95 mm
100 mm
See Figure 7-25.
193 mm
See Figure 7-26.
- Mark mounting holes on the mounting rails.
- Install the floating nuts and guide rails.
- Install the chassis in the cabinet.
- Install the removable handles on two sides of the chassis. Two persons lift the chassis using the handles several times to verify that the handles are installed correctly. See callout 1 in Figure 7-30.
- Three persons lift the chassis onto the guide rails from the front door and slowly push the chassis into one third of the cabinet depth. Hold the chassis while removing the removable handles. Then push the chassis completely in the cabinet. See callout 2 in Figure 7-30.
- Use screws to secure the chassis to the cabinet. See callout 3 in Figure 7-30.
- Hang the handles on the handle slots at rear of the chassis. See callout 4 in Figure 7-30.
- Connect the ground cable.