5288 V3 Server V100R003 User Guide 26

This document describes the features, appearance, and technical specifications of the 5288 V3 server, and how to install, power on, and power off the 5288 V3 server, connect cables, and install an operating system (OS) for it.
Rate and give feedback :
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installing the Server on Adjustable Guide Rails

Installing the Server on Adjustable Guide Rails

Adjustable guide rails apply to a cabinet with a distance of 543.5 mm to 848.5 mm (21.40 in. to 33.41 in.) between the front and rear mounting bars.

Procedure

  1. Install adjustable guide rails.

    1. Use a screwdriver to fasten one dowel pin on front and two dowel pins on the rear of the guide rail. ‎Figure 3-8 shows the positions of dowel pins.
      NOTE:

      Three types of dowel pins are shipped with the guide rails, and their diameters are 6.8 mm (0.27 in.), 8.7 mm (0.34 in.), and 9.2 mm (0.36 in.). Choose dowel pins with the largest diameter that can pass through the holes.

      Figure 3-8 Installing a dowel pin

    2. Place a guide rail horizontally in the planned position and stretch the guide rail and align the holes on the guide rail with the holes on the inner guide rail of the rack. Lead the front and rear dowel pins out of the holes to pre-position the guide rail. See step (1) in Figure 3-9.
      NOTE:

      Guide rails are divided into left and right guide rails (labeled with L and R). A pair of guide rails should be installed together and cannot be installed reversely.

      Figure 3-9 Installing an adjustable guide rail

    3. Use a screwdriver to tighten two screws on front and two screws on the rear of the guide rail. See step (2) in ‎‎Figure 3-9. The figure shows the positions of screws.
    4. Install another guide rail on the opposite side by using the same method.

  2. Install the 5288 V3.

    1. Lift the 5288 V3 and move it to the cabinet. This task requires at least four people.
    2. Place the 5288 V3 onto the guide rails and slide it into the cabinet. See step (1) in Figure 3-10.
      Figure 3-10 Installing the 5288 V3

    3. When the two mounting ears of the 5288 V3 come into contact with the mounting bars on the cabinet, tighten the captive screws on the mounting ears to secure the 5288 V3. See step (2) in Figure 3-10.

  3. After the installation is complete, connect a network cable, a VGA cable, or USB devices as required. Connect the power cables and power on the 5288 V3.
Translation
Download
Updated: 2018-11-26