5288 V3 Server V100R003 User Guide 26

This document describes the features, appearance, and technical specifications of the 5288 V3 server, and how to install, power on, and power off the 5288 V3 server, connect cables, and install an operating system (OS) for it.
Rate and give feedback :
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installing the Server on L-Shaped Guide Rails

Installing the Server on L-Shaped Guide Rails

L-shaped guide rails apply only to a Huawei cabinet.

Procedure

  1. Determine the positions for installing floating nuts. See Figure 3-3.

    Figure 3-3 Positions for installing floating nuts

  2. Install floating nuts.

    1. Determine the position for installing a floating nut based on the installation plan.
      NOTE:

      The floating nuts and screws are used together to tighten the screws.

      The middle of two adjacent square holes with small spacing is the boundary of two Us. See Figure 3-4. The boundary between Us is used as the reference for calculating device installation space.

      Figure 3-4 1U boundary lines on a mounting bar

    2. Fasten the lower end of a floating nut to the top square hole within the second target 1U space from top to bottom in a front mounting bar. See step (1) in Figure 3-5.
      Figure 3-5 Installing a floating nut

    3. Fasten the upper end of the floating nut to the mounting bar at the front of the cabinet by using the floating nut hook. See step (2) in Figure 3-5.

      The floating nut is installed, as shown in (3) in Figure 3-5.

    4. Install another floating nut in the top square hole within the bottom target 1U space using the same method.
    5. Install the other floating nuts using the same method.

  3. Install L-shaped guide rails.

    1. Place a guide rail horizontally in the designated position and keep the guide rail in contact with the mounting bars in the cabinet. See Figure 3-6.
      Figure 3-6 Installing an L-shaped guide rail

    2. Tighten the screws.
    3. Install the other guide rail on the opposite side by using the same method.

  4. Install the 5288 V3.

    1. Lift the 5288 V3 and move it to the cabinet. This task requires at least four people.
    2. Place the 5288 V3 onto the guide rails and slide it into the cabinet. See step (1) in Figure 3-7.
      Figure 3-7 Installing the 5288 V3

    3. When the two mounting ears of the 5288 V3 come into contact with the mounting bars on the cabinet, tighten the captive screws on the mounting ears to secure the 5288 V3. See step (2) in Figure 3-7.

  5. After the installation is complete, connect a network cable, a VGA cable, or USB devices as required. Connect the power cables and power on the 5288 V3.
Translation
Download
Updated: 2018-11-26

Document ID: EDOC1000080031

Views: 127246

Downloads: 2333

Average rating:
This Document Applies to these Products
Related Documents
Related Version
Share
Previous Next