KunLun 9016 V100R001 User Guide 12

This document describes the appearance, specifications, parameters, and structure of the KunLun 9016, and how to install an OS, replace parts, and install, remove, configure, and troubleshoot the server.
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Unpacking Components

Unpacking Components

Unpacking an SCE

Preparations
  • Precautions

    Do not unpack the system compute enclosure (SCE) before moving it to the equipment room.

  • Preparations for unpacking

    Check that the package is in good condition.

NOTE:

If the package is damaged (for example, the package is soaked or deformed, or the seals or pressure-sensitive adhesive tape is unsealed), fill in the Cargo Problem Feedback Form.

  • Tools
    • Protective gloves
    • ESD gloves
    • ESD wrist strap
    • Box cutter
Procedure
  1. Open the SCE package.

    Be careful when using a box cutter, to avoid personal injury or damage to components inside.

  2. Unpack the SCE.

    After unpacking the SCE, check the SCE components against Figure 3-77 and Table 3-8, and ensure that the components are in good condition, without defects such as oxidation, chemical corrosion, missing components, or other damage incurred during transport.

Figure 3-77 Unpacking an SCE

Table 3-8 Packing list

No.

Description

1

Accessory box

2

(Optional) A pair of adjustable guide rails

3

One SCE

4

A group of compute nodes

Unpacking a CME

Preparations
  • Precautions

    Do not unpack the central management enclosure (CME) before moving it to the equipment room.

  • Preparations for unpacking

    Ensure that the CME package is in good condition.

NOTE:

If the package is damaged (for example, the package is soaked or deformed, or the seals or pressure-sensitive adhesive tape is unsealed), fill in the Cargo Problem Feedback Form.

  • Tools
    • Protective gloves
    • ESD gloves
    • ESD wrist strap
    • Box cutter
Procedure
  1. Open the CME package.

    Be careful when using a box cutter, to avoid personal injury or damage to components inside.

  2. Unpack the CME.

    After unpacking the CME, check the CME components against Figure 3-78 and Table 3-9, and ensure that the components are in good condition, without defects such as oxidation, chemical corrosion, missing components, or other damage incurred during transport.

Figure 3-78 Unpacking a CME

Table 3-9 Packing list

No.

Description

1

Four partition interconnect cables (PICs)

2

(Optional) A pair of adjustable guide rails

3

One CME

Unpacking an REE

If the 9016 does not support REEs, skip this section.

Preparations
  • Precautions

    Do not unpack the REE before moving it to the equipment room.

  • Preparations

    Check whether the packing case and seals of the REE are in good condition.

NOTE:

If the packing case is damaged (for example, the packing case is soaked or deformed, or the seals or pressure-sensitive adhesive tape is unsealed), fill in the Cargo Problem Feedback Form.

  • Tools
    • Protective gloves
    • ESD gloves
    • ESD wrist strap
    • Box cutter
Procedure
  1. Open the REE package.

    Be careful with the box cutter to avoid personal injury or equipment damage.

  2. Unpack the REE.

    Check that the number of components is consistent with that specified in the Packing List and the components are in good condition, without defects such as oxidation, chemical corrosion, or other damage incurred during transport.

Figure 3-79 Unpacking an REE

Table 3-10 Shipped items

No.

Item

1

REE

2

Front bezel

Translation
Download
Updated: 2019-05-20

Document ID: EDOC1000111827

Views: 99904

Downloads: 250

Average rating:
This Document Applies to these Products
Related Documents
Related Version
Share
Previous Next