KunLun 9016 V100R001 User Guide 12

This document describes the appearance, specifications, parameters, and structure of the KunLun 9016, and how to install an OS, replace parts, and install, remove, configure, and troubleshoot the server.
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installing a Half-Height BIO (BIO-C or BIO-D)

Installing a Half-Height BIO (BIO-C or BIO-D)

Scenarios

Install a half-height back I/O module (BIO) to replace the faulty one.

Prerequisites

Conditions

The 9016 supports two types of half-height BIOs, BIO-D (7 slots) and BIO-C (8 slots). The following uses BIO-D as an example.

  • The BIO-D can be installed only in slots 1 and 3. The BIO-C can be installed only in slots 2 and 4. The slot numbers can be viewed on the right of the switch module. The slots are numbered 1, 2, 3, and 4 from left to right.
  • After a BIO of a different type is installed, do not power on the switch module within 2 minutes.

Data

No data preparation is required for this operation.

Tools

  • ESD gloves
  • Packaging materials, for example, an ESD bag

Hardware

Spare half-height BIO

Procedure

  1. Power off the physical partition where a BIO-D is to be installed. For details, see Powering Off the 9016.
  2. Take the spare BIO-D out of its ESD bag.
  3. Insert the BIO-D into the switch module as far as it will go. See step (1) in Figure 6-124.
  4. Close the ejector lever until the BIO-D is latched. See step (2) in Figure 6-124.

    Figure 6-124 Installing a BIO-D

Translation
Download
Updated: 2019-05-20

Document ID: EDOC1000111827

Views: 98753

Downloads: 248

Average rating:
This Document Applies to these Products
Related Documents
Related Version
Share
Previous Next