No relevant resource is found in the selected language.

This site uses cookies. By continuing to browse the site you are agreeing to our use of cookies. Read our privacy policy>Search

Reminder

To have a better experience, please upgrade your IE browser.

upgrade

KunLun 9016 V100R001 User Guide 12

This document describes the appearance, specifications, parameters, and structure of the KunLun 9016, and how to install an OS, replace parts, and install, remove, configure, and troubleshoot the server.
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installing a Front Bezel

Installing a Front Bezel

Scenarios

Install a front bezel.

Prerequisites

Conditions

No special condition is required for this operation.

Data

No data preparation is required for this operation.

Tools

  • ESD gloves
  • Packaging materials, for example, an ESD bag

Hardware

Spare front bezel

Procedure

  1. Take the spare front bezel out of the ESD bag.
  2. Align the front bezel with the connectors in the enclosure, and insert the front bezel into the enclosure in the arrow direction until the front bezel is secured to the enclosure. See Figure 6-12.

    Figure 6-12 Installing a front bezel

Translation
Download
Updated: 2019-05-20

Document ID: EDOC1000111827

Views: 105159

Downloads: 251

Average rating:
This Document Applies to these Products
Related Documents
Related Version
Share
Previous Next