Installing an NCM
Scenarios
Install a node controller module (NCM) to replace the faulty one.
Prerequisites
Conditions
No special conditions are required for this operation.
Data
No data preparation is required for this operation.
Tools
- ESD gloves
- Packaging materials, for example, an ESD bag
Hardware
Spare NCM
Procedure
- Power off the physical partition where an NCM is to be installed. For details, see Powering Off the 9016.
- Take the spare NCM out of its ESD bag.
- Insert the NCM into the SCE as far as it will go. See step (1) in Figure 6-42.
- Close the NCM ejector lever until the NCM is latched. See step (2) in Figure 6-42.
- Connect the node interconnect (NI) cables to the NCM. Install NI cables see Connecting NI Cables.