No relevant resource is found in the selected language.

This site uses cookies. By continuing to browse the site you are agreeing to our use of cookies. Read our privacy policy>Search

Reminder

To have a better experience, please upgrade your IE browser.

upgrade

KunLun 9016 V100R001 User Guide 12

This document describes the appearance, specifications, parameters, and structure of the KunLun 9016, and how to install an OS, replace parts, and install, remove, configure, and troubleshoot the server.
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installing a Supercapacitor (Switch Module)

Installing a Supercapacitor (Switch Module)

Scenarios

Install a supercapacitor in a switch module in any of the following scenarios:

  • A supercapacitor in the switch module has failed.
  • A supercapacitor is low.

Prerequisites

Conditions

No special condition is required for this operation.

Data

No data preparation is required for this operation.

Tools

  • ESD gloves
  • Packaging materials, for example, an ESD bag
  • Phillips screwdriver

Hardware

Spare supercapacitor

Procedure

  1. Power off the SCE where a supercapacitor is to be installed. For details, see Powering Off the 9016.
  2. Remove the switch module. For details, see Removing a Switch Module.
  3. Press the button on the switch module cover. See step (1) in Figure 6-141.
  4. Remove the cover. See steps (2) and (3) in Figure 6-141.

    Figure 6-141 Remove the cover

  5. Remove the air duct from the switch module. For details, see Removing an Air Duct.
  6. Take the spare supercapacitor out of its ESD bag.
  7. Align the supercapacitor with the RAID control card, and tighten the screws. See steps (1) and (2) in Figure 6-142.

    Figure 6-142 Installing a supercapacitor

  8. Place the air duct from the switch module. For details, see Installing an Air Duct.
  9. Place the cover onto the switch module. See step (1) in Figure 6-143.
  10. Gently push the cover until it snaps into place. See step (2) in Figure 6-143.

    Figure 6-143 Installing the switch module cover

Translation
Download
Updated: 2019-05-20

Document ID: EDOC1000111827

Views: 105083

Downloads: 251

Average rating:
This Document Applies to these Products
Related Documents
Related Version
Share
Previous Next