KunLun 9016 V100R001 User Guide 12

This document describes the appearance, specifications, parameters, and structure of the KunLun 9016, and how to install an OS, replace parts, and install, remove, configure, and troubleshoot the server.
Rate and give feedback :
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installing a PFM in the CME

Installing a PFM in the CME

Scenarios

Install a power and fan integrity module (PFM) in the central management enclosure (CME) in any of the following scenarios:

  • The PFM has failed.
  • The PFM needs to be replaced with a new model.

Prerequisites

Conditions

No special conditions are required for this operation.

Data

No data preparation is required for this operation.

Tools

  • ESD gloves
  • Packaging materials, for example, an ESD bag

Hardware

Spare PFM

Procedure

  1. Take the spare PFM out of its ESD bag.
  2. Slide the PFM into the CME as far as it will go. See step (1) in Figure 6-22.
  3. Close the ejector lever on the PFM until the PFM is latched. See step (2) in Figure 6-22.
  4. Connect the cable to the PFM. See step (3) in Figure 6-22.

    Figure 6-22 Installing a PFM

Translation
Download
Updated: 2019-05-20

Document ID: EDOC1000111827

Views: 84199

Downloads: 245

Average rating:
This Document Applies to these Products
Related Documents
Related Version
Share
Previous Next