Checking After Commissioning
Table 4-14 lists the commissioning checklist.
Check Item |
Actual Result |
---|---|
No oil stain exists on the copper pipe thermal insulation foam or bottom plate, or it has been cleaned. |
□ Passed □ Failed |
The needle valve plug is secured (torque of 0.45±0.05 N·m), and valve bonnet is tightened. |
□ Passed □ Failed |
The foreign matter inside the water pan and bottom plate is cleaned up. |
□ Passed □ Failed |
The air filter is correctly installed according to the air flow direction on the frame. |
□ Passed □ Failed |