Configuration Guide - DCN and Server Management

CloudEngine 8800, 7800, 6800, and 5800 V200R003C00

This document describes the configurations of Trill, FCoE, DCB, and NLB Server Cluster Association.
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
NPV

NPV

A SAN allows a maximum of 239 switches. When more edge switches are required, NPV switches that do not consume domain IDs can be deployed.

Figure 2-8 NPV networking

As shown in Figure 2-8, an NPV switch is located at the edge of a fabric and between an ENode and an FCF. The NPV switch uses an F_Port to connect to an N_Port of an ENode and uses an NP_Port to connect to an F_Port of an FCF. The ENode connects to the fabric through the NPV switch, and the NPV switch forwards traffic from all ENodes to the core switch.

For an ENode, an NPV switch is an FCF that provides an F_Port. For an FCF, an NPV switch is an ENode that provides N_Port.

Translation
Download
Updated: 2019-05-08

Document ID: EDOC1100004349

Views: 31670

Downloads: 120