Power Adjustment Description
According to standard requirements, the SmartLogger can reliably adjust power for the connected inverters in real time to ensure that the PV plant can respond to requirements of the power grid company in a timely manner.
Two power grid scheduling modes are available: active power control and reactive power control.
Active Power Control
If the PV plant has requirements of power limitation, the power grid scheduling personnel should limit the active power or disable all the active power for the PV plant, that is, to enable the active power derating mode.
Because of permission restriction, log in as Special User. Choose to access the target page.
Reactive Power Control
Large-scale PV plants are required to adjust the voltage at the grid-tied point. Power grid scheduling personnel enable the PV plant to absorb or add the reactive power at the grid-tied point, that is, to enable the reactive power compensation, based on the real-time reactive power transmission status in the power grid.
Because of permission restriction, log in as Special User. Choose to access the target page.