Active Power Control
- If the PV plant has requirements of power limitation, the power grid scheduling personnel should limit the active power or disable all the active power for the PV plant, that is, to enable the active power derating mode.
- The active power control mode includes the following:
No limit ,DI active scheduling ,Percentage fixed-value limitation (open loop) ,Remote communication scheduling ,Grid connection with limited power (kW) , andRemote output control .
- Log in as Special User, go to the Active power control page, set active power control parameters, and click Submit.Figure 8-3 Active Power Control