Power-on Process
This section describes how to check the SmartLogger before power-on and how to power on the SmartLogger.
Checking Before Powering On the SmartLogger
- All cables are intact and well insulated.
- All cables are of proper size.
- All cables are correctly connected and secured.
Power-on Process
Power on the devices in the following sequence: Inverter > SmartLogger > PC terminal.
The PC terminal refers to a PC where the NetEco1000 is installed.
Step |
Operation |
---|---|
1 |
Perform the requirements mentioned in Checking Before Powering On the SmartLogger. |
2 |
Start the inverter and correctly set the communications parameters (including Address, and Baud rate). For details about how to set communications parameters, see the user manual of the corresponding inverter or SUN2000 APP User Manual. |
3 |
Connect the output terminal of the power adapter for the SmartLogger to the power port POWER and the input terminal to the AC socket. |
4 |
Set the search address segment and baud rate for the RS485 port on the SmartLogger monitoring panel. If the SmartLogger is powered on for the first time, set the search address segment and baud rate for the RS485 port in the Wizard, as shown in Setting Initialization Parameters. If it is not powered on for the first time, set the parameters in the under the , as shown in Setting Communications Parameters. |
5 |
Wait for the SmartLogger to search for inverters. After the search is completed, the SmartLogger automatically connects to all inverters. Alternatively, you can skip this operation and manually search for, add, or delete inverters in follow-up operations. For details, see Managing Devices. |
6 |
(Optional) Manually add an environment monitoring instrument, power meter, PLC (MBUS), or third-party device. For details, see Managing Devices. NOTICE:
Before adding an environment monitoring instrument or power meter, log in to the WebUI and correctly set parameters for the device to be added. Before adding a third-party device, import a correct configuration file for the device. |
7 |
(Optional) Start the PC and correctly set parameters of the Ethernet and management system on the SmartLogger. |
- Use the delivered 12 V power adapter when starting the SmartLogger. Confirm with the local Huawei engineers if using other types of power adapters.
- Log in to the SmartLogger on the monitoring panel. When you log in to the 000001. page or page, an identity authentication is required. The initial password is
- Use the initial password upon first power-on and change it immediately after login. To ensure account security, change the password periodically and keep the new password in mind. Not changing the initial password may cause password disclosure. A password left unchanged for a long period of time may be stolen or cracked. If a password is lost, devices cannot be accessed. In these cases, the user is liable for any loss caused to the PV plant.