OSN 500 550 580 V100R008C50 Commissioning and Configuration Guide 02

Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Creating EPL Services

Creating EPL Services

When an Ethernet switching board carries private line services, the relevant information of the private line services, such as the service source and service sink, must be specified.

Prerequisites

You are an NM user with Operator Group rights or higher.

Procedure

  1. In the NE Explorer, select the Ethernet board and choose Configuration > Ethernet Service > Ethernet Line Service from the Function Tree.
  2. Select the proper operation from the following options according to the type of the EPL services to be created.
    Option Description
    EPL services Proceed to Step 3.
    EVPL (QinQ) services Select Display QinQ Shared Service.
  3. Click New.

    The Create Ethernet Line Service dialog box is displayed.

  4. Set the attributes of the private line service.



  5. Set the attributes of the source port and sink port.

    Figure 2-85  Attributes of the ports on the Ethernet boards that support the QinQ function

  6. Set the VC paths to be bound with the internal ports.
    1. Click Configuration.

      The Bound Path Configuration dialog box is displayed.

    2. In Configurable Ports, select a VCTRUNK as the port to be configured.
    3. In Available Bound Paths, set Level and Direction of the bound paths.
    4. Select the required items in Available Resources and Available Timeslots and click .
    5. Repeat Steps 6.b to 6.d and bind other VC paths.
    6. Click OK.

      NOTE:

      The timeslots on the transmission line that correspond to the paths bound with the VCTRUNKs at both ends of the transmission line must be consistent.

  7. Click OK.

    The Operation Result dialog box is displayed indicating that the operation is successful.

Translation
Download
Updated: 2019-01-21

Document ID: EDOC1100020976

Views: 50575

Downloads: 409

Average rating:
This Document Applies to these Products
Related Version
Related Documents
Share
Previous Next