Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installing an M.2 SSD

Installing an M.2 SSD

Procedure

  1. Power off the G560 V5. For details, see Powering Off the Compute Node.
  2. Remove the G560 V5. For details, see Removing the G560 V5.
  3. Place the G560 V5 on the ESD floor.
  4. Remove the cover. For details, see Removing the Cover of the G560 V5.
  5. Determine the position of the M.2 SSD to be installed. See Figure 5-6.

    Figure 5-6 Position of the M.2 SSD

  1. Take a spare M.2 SSD out of its ESD bag.
  2. Install the M.2 SSD in the slot. See (1) in Figure 5-7.

    Figure 5-7 Installing an M.2 SSD

  3. Use an M2.5 Phillips screwdriver to tighten the screw that secures the M.2 SSD. See (2) in Figure 5-7.
  1. Install the cover. For details, see Installing the Cover of the G560 V5.
  2. Install the G560 V5. For details, see Installing the G560 V5.
  3. Power on the G560 V5. For details, see Powering On the Compute Node.
Translation
Download
Updated: 2018-12-14

Document ID: EDOC1100031433

Views: 41565

Downloads: 107

Average rating:
This Document Applies to these Products
Related Version
Related Documents
Share
Previous Next