Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installing a Server Node

Installing a Server Node

Operation Scenario

NOTICE:

The X6800 supports mixed configuration of XH628 V5 and XH628 V3 server nodes. In this case, the operating temperature of the server is the same as that of the XH628 V5 server node.

You need to install a server node in any of the following scenarios:

  • A chassis has been installed.
  • A server node needs to be added.
  • A server node needs to be replaced with a new one.
  • A server node has been repaired.

Procedure

  1. Wear an ESD wrist strap or ESD gloves.
  2. Take the spare server node out of the ESD bag, and raise the ejector lever.
  3. Horizontally insert the server node into a slot in the chassis, and ensure that the upper side of the ejector lever is fastened to the chassis beam. See (1) in Figure 3-11.

    Figure 3-11 Installing a server node

  4. Lower the ejector lever until its lower side snaps into the release button. See (2) in Figure 3-11.
Translation
Download
Updated: 2018-08-28

Document ID: EDOC1100036738

Views: 9308

Downloads: 33

Average rating:
This Document Applies to these Products
Related Documents
Related Version
Share
Previous Next