Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installing an XH628 V5

Installing an XH628 V5

Procedure

  1. Determine the position of the server node in the chassis.

    Figure 3-7 Positions and slot numbers of the XH628 V5 server nodes
    NOTE:

    Install the XH628 V5 nodes into the chassis from left to right.

  2. Remove filler panels.

    NOTE:

    Perform this operation only when filler panels are installed.

    1. Gently push the release button on the filler panel. See (1) in Figure 3-8.
    2. Hold the ejected side of the filler panel, and pull it out of the chassis. See (2) in Figure 3-8.
    Figure 3-8 Removing the filler panel
    1. Place the removed filler panel in an accessory recycle bin.

  3. Install the server node.

    To prevent device damage or personal injury, hold the bottom of the device with both hands when installing it.

    1. Press the ejector latch on the server node. See (1) in Figure 3-9.
    2. Fully open the ejector lever. See (2) in Figure 3-9.
    3. Slide the server node into the chassis horizontally. See (3) in Figure 3-9.
    Figure 3-9 Installing a server node
    1. Close the ejector lever.

  4. Connect the multi-port cable as required.

    1. Press the two tabs on the multi-port cable connector. See (1) in Figure 3-10.
    2. Connect the multi-port cable to the UCP on the server. See (2) in Figure 3-10.
    Figure 3-10 Connecting a multi-port cable

  5. Power on the server node.

    For details, see Power-On Procedure.

  6. Check indicator status.

    For details, see Indicators and Buttons.

Translation
Download
Updated: 2019-08-12

Document ID: EDOC1100036739

Views: 15380

Downloads: 20

Average rating:
This Document Applies to these Products
Related Documents
Related Version
Share
Previous Next