Site Planning Guide

OceanStor Dorado18000 V3 V300R002

This document describes the division of responsibilities between Huawei and customers during the deployment of the Dorado18000 V3 storage system and the tasks that need to be completed before the installation.
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Floor Deployment Planning

Floor Deployment Planning

Before planning how to install the Dorado18000 V3 storage system on raised floors or non-raised floors, learn about the system dimensions, deployment options, and floor area requirements to ensure that the planned space is sufficient for system deployment.

Device Dimensions

Table 4-1 and Table 4-2 describe the dimensions of a system bay and the width of a multi-bay.

Table 4-1 Width of a multi-bay Dorado18000 V3 storage system

Parameter

System Bay

Height

2000 mm

Width

600 mm

Depth

1232 mm

NOTE:

The dimensions in Table 4-1 are a bay's maximum dimensions including the dimensions of wheels and base anchors.

Table 4-2 Width of a multi-bay

Number of Bays

Widtha

1

600 mm

2

1207 mm

a: Leave a 6 mm to 8 mm space between every two bays so that the front door of the bay on the right can move freely when the front door of the bay on the left is fully open. The space is calculated by assuming the space between every two bays is 7 mm.

Floor Planning

When placing the floors, note the requirements of device installation and deployment, raised floors and non-raised floors, floor tile cuts, and ventilation.

If an equipment room adopts the underfloor flow mode, provide each bay with a ventilation floor whose ventilation rate is greater than or equal to 0.5.

When deploying a bay on a raised floor, align the bay columns with the floor seams. If adopting the underfloor cabling mode, cut the floor. When a single bay is installed, the location and size of the cut is shown in Figure 4-1.

Figure 4-1 Location and size of the cut

Translation
Download
Updated: 2019-07-17

Document ID: EDOC1100049134

Views: 5825

Downloads: 20

Average rating:
This Document Applies to these Products
Related Version
Related Documents
Share
Previous Next