- About This Document
- Safety Operation Guide
- Installation Process
- Installation Preparations
- Unloading and Transporting Equipment
- Unpacking and Checking Equipment
- Installing a Huawei Cabinet
- Checking a Third-Party Cabinet
- Installing Components in a Cabinet
- Removing Filler Panels from the Cabinet
- Determining Installation Locations
- Installing Guides Rails and Floating Nuts
- Installing a 2288H V5 12-Slot Node
- Installing a 5288 V5 36-Slot Node
- Installing a TaiShan 2280 12-Slot Node
- Installing a TaiShan 5280 36-Slot Node
- Installing a TaiShan 2280 V2 12-Slot Node
- Installing a TaiShan 5280 V2 36-Slot Node
- Installing a 10GE/25GE Switch
- Installing a GE Switch
- Installing a KVM
- Installing PGND Cables and Power Cables Between Components in a Cabinet
- Connecting a Power Cable for a 2288H V5 12-Slot Node
- Connecting a Power Cable for a 5288 V5 36-Slot Node
- Connecting a Power Cable for a TaiShan 2280 12-Slot Node
- Connecting a Power Cable for a TaiShan 5280 36-Slot Node
- Connecting a Power Cable for a TaiShan 2280 V2 12-Slot Node
- Connecting a Power Cable for a TaiShan 5280 V2 36-Slot Node
- Installing a PGND Cable and Power Cable for a CE6855/CE6865 Switch
- Installing a PGND Cable and Power Cable for a CE5855 Switch
- Installing a PGND Cable and Power Cable for a KVM
- Connecting Signal Cables
- Checking the Installation
- Installing a Filler Panel in a Cabinet
- Powering On Devices
- Appendix