No relevant resource is found in the selected language.

This site uses cookies. By continuing to browse the site you are agreeing to our use of cookies. Read our privacy policy>Search

Reminder

To have a better experience, please upgrade your IE browser.

upgrade

NE40E V800R010C10SPC500 Installation Guide

This is NE40E V800R010C10SPC500 Installation Guide
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installing Power Cables of the DACS PDB

Installing Power Cables of the DACS PDB

Installation Procedures

  1. Install the input power cable for the PDB. Connect the power cable to the input terminal of the DACS through the cable suite. Lead one end of the input power cable of the PDB to the AC power distribution panel along the cable tray.
    Figure 15-5 Installing power cables of the PDB

    NOTE:
    • In a three-phase 63 A input short-circuit scenario, use the copper fittings delivered with the PDB to connect L1 and L2 of A1 and L1 and L2 of A2, respectively. The input terminals on the right are connected in the same way.

    • In a single-phase 63 A input short-circuit scenario, use the copper fittings delivered with the PDB to connect A1 and A2 of L1, A1 and A2 of L2, A1 and A2 of L3, and A1 and A2 of N, respectively. The input terminals on the right are connected in the same way.

  2. Install the output power cable of the PDB. Connect the router and the DACS according to the connections described in the application example.

  3. The following figure shows how to fix the power cables onto the C19 terminal sides of the AC/AC power modules.

    Connect the C19-C20 cable to the terminal. Pull the locking strap to the end of the cable to fasten the cable. Buckle the cable.





Do not install power cables when the power is on.
Translation
Download
Updated: 2019-01-03

Document ID: EDOC1100055059

Views: 39606

Downloads: 286

Average rating:
This Document Applies to these Products
Related Documents
Related Version
Share
Previous Next