NE40E V800R010C10SPC500 Installation Guide

This is NE40E V800R010C10SPC500 Installation Guide
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
AC Power Distribution

AC Power Distribution

Power Distribution Principle

NOTE:
  • One PM outputs a maximum of 2700 W power. You can configure PMs based on the required power.
  • PMs work in N+N backup mode. N PMs (N >= 1) are configured on planes A and B, respectively. The PMs are backed up in the pair of A1 and B1, A2 and B2, A3 and B3, and so on.
  • Note that different power sources must be provided for PMs on planes A and B so that one can provide power when the other becomes faulty.

Power Distribution Instance

Power Consumption

PM Configurations

2700 W

One pair of PMs, A1 and B1

5400 W

Two pairs of PMs, A1 and B1, A2 and B2

8100 W

Three pairs of PMs, A1 and B1, A2 and B2, A3 and B3

10800 W

Four pairs of PMs

Cable and Terminal Specifications

The PDF requires protection components to ensure that the rated current of each channel is not less than 16 A. The following table shows the cable and terminal specifications.

Table 10-4 Cable and terminal specifications

Item

Description

Huawei BOM Number

AC input cables

External Suite, Power Cords All Over The World, Class I Equipment With Connector C19, External Cable Set

04000408 or 04000207

NOTE:

Choose cables in the package according to standards in various countries and areas.

Installing power cables

Do not install power cables when the power is on.

  1. Install PMs.
    Figure 10-31 Installing PMs

  2. Attach temporary labels to both ends of each power cable.
  3. Route AC power cables along the cable ladder and connect them to the input terminals of the AC power distribution box. Connect the other end of each power cable to the PDF in the equipment room.
  4. After cables are inserted to the terminals, use cable fasteners to secure the cables to the terminals.
  5. Use cable ties to bundle the cables every 150 mm (5.91 in.) upwards from the bottom end, and secure the cables to the cable tray.
  6. Attach permanent labels 20 mm (0.79 in.) from both ends of each power cable.
    Figure 10-32 Installing power cables

Translation
Download
Updated: 2019-01-03

Document ID: EDOC1100055059

Views: 39947

Downloads: 286

Average rating:
This Document Applies to these Products
Related Version
Related Documents
Share
Previous Next