NE40E-M2 V800R010C10SPC500 Configuration Guide - WAN Access 01

This is NE40E-M2 V800R010C10SPC500 Configuration Guide - WAN Access

Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Configuring a POS-Trunk Interface

Configuring a POS-Trunk Interface

Before configuring a POS-Trunk interface, familiarize yourself with the usage scenario, complete the pre-configuration tasks, and obtain the data required for the configuration.

Context

To configure APS on POS interfaces, create a POS-Trunk interface and add the POS interfaces to the POS-Trunk interface.

Pre-configuration Tasks

Before configuring a POS-Trunk interface, power on the devices and check that the self-check succeeds.

Configuration Procedures

Figure 3-2 Flowchart for configuring a POS-Trunk interface

Creating a POS-Trunk Interface

Before bundling physical interfaces into a POS-Trunk interface, create this POS-Trunk interface.

Procedure

  1. Run system-view

    The system view is displayed.

  2. Run interface pos-trunk trunk-id

    A POS-Trunk interface is created.

  3. Run commit

    The configuration is committed.

Adding a POS Interface to a POS-Trunk Interface

After creating a POS-Trunk interface, add a POS interface to the POS-Trunk interface.

Procedure

  1. Run system-view

    The system view is displayed.

  2. Run interface pos interface-number

    The view of the POS interface to be added to a POS-Trunk interface is displayed.

  3. Run link-protocol ppp

    The link layer protocol of the POS interface is configured as PPP.

    NOTE:

    The link layer protocol of POS interfaces added to a POS-Trunk interface must be configured as PPP.

  4. Run pos-trunk trunk-id

    The POS interface is added to a POS-Trunk interface.

  5. Run commit

    The configuration is committed.

Verifying the POS-Trunk Interface Configuration

After completing the basic configurations of a POS-Trunk interface, check the configurations.

Prerequisites

Basic configurations have been completed on a POS-Trunk interface.

Procedure

  • Run the display pos-trunk trunk-id command to check the configurations of a POS-Trunk interface.

Example

Run the display pos-trunk trunk-id command. The command output shows the configurations of a POS-Trunk interface.
<HUAWEI> display pos-trunk 1
Interface Pos-Trunk1's state information is:
Operate status: up     Number Of Up Port In Trunk: 2
--------------------------------------------------------------------------------
PortName    Status    Active Status
Pos1/0/1    Up        Inactive
Pos1/0/2    Up        Active     
Download
Updated: 2019-01-02

Document ID: EDOC1100058399

Views: 17566

Downloads: 61

Average rating:
This Document Applies to these Products

Related Version

Related Documents

Share
Previous Next