AMI Smart Meter Reading Solution V200R010C10 Planning and Design Guide

This document describes the overall and detailed design of functions and services in the AMI Smart Meter Reading Solution.
Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
DCC Design principles

DCC Design principles

A Data Connection Converter (DCC) is deployed between a DCU and a smart meter. A smart meter can connect to a DCU through a DCC or directly connect to a DCU. You need to select DCCs based on the onsite situation and customer requirements. Table 4-3 describes DCC design principles and selection factors.
Table 4-3  DCC selection

Scenario

Factor

Selection

Power grid environment

There is a high density of smart meters, but smart meters are sparsely distributed.

Smart meters communicate with DCCs through RS485, and DCCs communicate with DCUs through PLC.

Multi-meter boxes are installed in a centralized manner.

DCCs can be used to implement communication between DCUs and smart meters.

Translation
Download
Updated: 2019-03-07

Document ID: EDOC1100069579

Views: 6080

Downloads: 9

Average rating:
This Document Applies to these Products
Related Version
Related Documents
Share
Previous Next