Powering on the Atlas 200 DK Developer Board
Precautions
Do not power off the Atlas 200 DK developer board while it is booting for the first time. Otherwise, the developer board may be damaged. To re-power on the developer board, wait at least 2s after it is powered off.
Procedure
- Plug in the power cable and connect the power module to the external power supply. Figure 9-1 shows the power interface on the Atlas 200 DK developer board. Connect to the power supply, the Atlas 200 DK developer board automatically boots.
1
Power indicator
2
Power interface
3
USB port
4
MicroSD card
5
Network port
6
Reset key
- Check the status of the indicator to ensure that the Atlas 200 DK developer board is powered on properly.
The following tables describe the LED indicator states.
Table 9-1 State description of LED 1 and LED 2LED 1
LED 2
Status of the Atlas 200 DK Developer Board
Precautions
Off
Off
Atlas 200 DK Developer Board Booting
You can power off or restart the Atlas 200 DK developer board.
Off
On
Booting the Ascend 310
You can power off or restart the Atlas 200 DK developer board except during version upgrade.
Blinking
Blinking
Upgrading the firmware
Do not power off or restart the Atlas 200 DK developer board. Otherwise, the firmware upgrade may be incomplete and the board may be damaged.
The firmware upgrade process is a part of the version upgrade. The upgrade takes about 15 minutes.
On
On
Atlas 200 DK Developer Board Boot finished
You can power off or restart the Atlas 200 DK developer board.