FusionStorage 8.0.0 Block Storage Hardware Installation Guide 06

Rate and give feedback:
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installation Process

Installation Process

Learning about the installation process prior to installing FusionStorage block storage will greatly facilitate the subsequent operations.

Figure 2-1 and Table 2-1 respectively provide an installation flowchart and step-by-step instructions.

Figure 2-1 Installation flowchart
Table 2-1 Step-by-step instructions

Key Step

Description

Installation Preparations

Before installing the equipment, ensure that:

  • All required documents and installation tools are ready.
  • You have verified the installation environment and device specifications.
  • You have planned the networks and created the network diagrams.

Unloading and Transporting Equipment

Operators must understand safety precautions and choose appropriate tools for unloading and transporting the equipment.

Unpacking and Checking Equipment

When the equipment arrives, project supervisors and customer representatives must unpack devices together and ensure that devices are intact and the quantity is correct.

Installing a Huawei Cabinet

Install the accompanying cabinet.

Checking a Third-Party Cabinet

Check the cabinet provided by a third party to ensure that it meets device installation conditions.

Installing Components in a Cabinet

Install equipment components into a cabinet in sequential order from bottom to top.

Installing PGND Cables and Power Cables Between Components in a Cabinet

Install PGND cables and power cables.

Connecting Signal Cables

Install signal cables.

Checking the Installation

Check hardware installation to ensure that devices work properly.

Installing a Filler Panel in a Cabinet

Install filler panels to ensure efficient electromagnetic shielding, sufficient ventilation, and outstanding dust-proof performance.

Powering On Devices

Power on the equipment and verify that the equipment is working correctly after power-on.

Download
Updated: 2019-11-14

Document ID: EDOC1100081415

Views: 6729

Downloads: 13

Average rating:
This Document Applies to these Products
Related Version
Related Documents
Share
Previous Next