Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document. Note: Even the most advanced machine translation cannot match the quality of professional translators. Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installing a TaiShan 5280 V2 36-Slot Node

Installing a TaiShan 5280 V2 36-Slot Node

Installing a TaiShan 5280 V2 36-slot node into the cabinet includes sliding the node into the cabinet, fastening the node, and checking the installation.

Prerequisites

  • Operations described in Installing a Huawei Cabinet or Checking a Third-Party Cabinet have been completed.
  • Holding rails have been installed.
  • All required tools have been prepared, including M3 to M6 Phillips screwdrivers, M6 screws, and protective gloves.
  • The CPU, DIMM, riser card, PCIe card on the riser card, PCIe card, and built-in disks (optional) of the node have been installed. If any of the parts is not installed, see related contents of the TaiShan 5280 V2 36-slot node in Parts Replacement to install it.

Context

  • A fully configured TaiShan 5280 V2 36-slot node weighs up to 65 kg. Arrange for at least four persons to carry it and ensure that they wear protective gloves to avoid personal injury.
  • Install components into a cabinet from bottom to top to prevent the cabinet from falling over.

Procedure

  1. Wear an ESD wrist strap or ESD gloves.
  2. Install a TaiShan 5280 V2 36-slot node.

    1. Pull out inner rails from holding rails until the inner rails cannot move, push the release buttons upward, and remove the inner rails from the holding rails, as shown in steps 1 and 2 in Figure 8-49.
      Figure 8-49 Pulling out an inner rail
    1. Align the screws on the node with the notches on the inner rails, push the node inwards until you hear a sound, and ensure that the latches eject and completely block the screws to affix the node to the inner rails. See Figure 8-50.
      Figure 8-50 Installing an inner rail
    1. Arrange for at least four persons to lift the node, align the inner rails on the node with the holding rails, and push the node into the holding rails, as shown in Figure 8-51.
      Figure 8-51 Pushing the node into holding rails
    1. Press the release buttons on both sides, and push the node into the cabinet until the node cannot move forward, as shown in Figure 8-52.
      Figure 8-52 Pushing the node into a cabinet
    1. Tighten the captive screws on the mounting ears to secure the node, as shown in Figure 8-53.
      Figure 8-53 Securing the node

  3. Optional: Install disks.

    1. Fully raise the ejector lever and push a disk into the chassis along the guide rails until it does not move. See step 1 in Figure 8-54.

    To ensure favorable heat dissipation, insert disks in the sequence of disk slot numbers. If disk modules or PCIe cards are not fully configured, install filler panels into vacant disk or PCIe slots.

    Figure 8-54 Installing a disk
    1. Ensure that the ejector lever is fastened to the chassis beam, and lower the ejector lever to completely insert the disk into the chassis. See step 2 in Figure 8-54.

Download
Updated: 2019-11-14

Document ID: EDOC1100081415

Views: 7826

Downloads: 15

Average rating:
This Document Applies to these Products
Related Version
Related Documents
Share
Previous Next