SUN2000-(75KTL, 100KTL, 110KTL, 125KTL) Series User Manual
This document describes the SUN2000-(75KTL,100KTL, 110KTL, 125KTL) series in terms of their installation, electrical connections, commissioning, maintenance, and troubleshooting.
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document.
Note: Even the most advanced machine translation cannot match the quality of professional translators.
Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Connecting the PE Cable
Connecting the PE Cable
Context
Proper grounding is helpful for resisting the impact of surge voltage and improving the electromagnetic interference (EMI) performance. Before connecting the AC power cable, DC power cables, and communications cable, connect the PE cable to the PE point.
You are advised to choose the ground point on the enclosure. The ground point in the maintenance compartment is used for connecting to the PE cable contained in the multi-core AC power cable.
It is recommended that the PE cable of the solar inverter be connected to a nearby ground point. Connect the PE points of all solar inverters in the same array to ensure equipotential connections to PE cables.
Procedure
Connect the PE cable to the PE point.
Figure 5-6 Connecting the PE cable to the PE point (on the enclosure)
(1) Reserved PE point
Follow-up Procedure
To enhance the corrosion resistance of a ground terminal, apply silica gel or paint on it after connecting the PE cable.