No relevant resource is found in the selected language.
Your browser version is too early. Some functions of the website may be unavailable. To obtain better user experience, upgrade the browser to the latest version.
SUN2000-(75KTL, 100KTL, 110KTL, 125KTL) Series User Manual
This document describes the SUN2000-(75KTL,100KTL, 110KTL, 125KTL) series in terms of their installation, electrical connections, commissioning, maintenance, and troubleshooting.
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document.
Note: Even the most advanced machine translation cannot match the quality of professional translators.
Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Check Before Power-on
Check Before Power-on
No.
Acceptance Criteria
1
The solar inverter is installed correctly and securely.
2
The DC switches and the downstream AC switch are OFF.
3
All cables are connected correctly and securely.
4
The installation space is proper, and the installation environment is clean and tidy.
5
The maintenance compartment door is closed and the door screws are tightened.
6
Unused DC input terminals are sealed.
7
Unused USB and RESET ports are plugged with watertight caps.