Installing the Air Duct
Procedure
- Power off the server.
For details, see Power-Off Procedure.
- Remove the power cables from the PSUs.
For details, see Removing PSU Cables.
- Remove the server.
For details, see Removing the Server.
- Place the server on the ESD workstation.
- Remove the chassis cover.
For details, see Removing the Chassis Cover.
- Check whether a full-height full-length PCIe riser module is installed.
- Remove the full-height full-length PCIe riser module.
For details, see Removing a PCIe Riser Module.
- Take the spare part out of its ESD bag.
- Determine the position of the air duct.
- Align the positioning pins on the air duct with the fixing holes on the chassis according to the instructions on the air duct. Vertically place the air duct downwards.Figure 6-184 Installing the air duct
- Check whether a supercapacitor is configured.
- Connect the cable between the supercapacitor and the TFM card.Figure 6-185 Connecting the supercapacitor cable
- Check whether a full-height full-length PCIe riser module is installed.
- Install the full-height full-length PCIe riser module.
For details, see Installing a PCIe Riser Module.
- Install the chassis cover.
For details, see Installing the Chassis Cover.
- Install the server.
For details, see Installing a Server.
- Connect the power cables to the PSUs.
For details, see Connecting PSU Cables.
- Power on the server.
For details, see Power-On Procedure.
- Log in to the iBMC WebUI, and check whether the new component is normal.
For details, see Atlas 800 Inference Server iBMC User Guide (Model 3010).