Checking Before Power-On
No. |
Acceptance Criteria |
---|---|
1 |
The cabinet and all components are installed properly. |
2 |
All upstream switches for the cabinet and all switches inside the cabinet are OFF. |
3 |
All cables are connected correctly and securely, without exposed metal. |
4 |
Cables are bound neatly, and cable ties are secured evenly and properly in the same direction. |
5 |
Routing for the power cables and signal cables meets the requirements for routing strong-current and weak-current cables and complies with the cable routing plan. |
6 |
The locking caps of the used waterproof connectors are tightened and sealed. Idle waterproof connectors are plugged and the locking caps are tightened. |
7 |
The cabinet interior is clean, without dust, dirt, or foreign matter. |
8 |
The paint on the cabinet exterior is intact. If paint flakes off, repaint that area to prevent corrosion. |