Routine Maintenance
To ensure that the SUN2000 can operate properly for a long term, you are advised to perform routine maintenance on it as described in this chapter.
Before cleaning the SUN2000, connecting cables, and maintaining the grounding reliability, power off the SUN2000 (see System Power-Off for details).
Check Item |
Check Method |
Maintenance Interval |
---|---|---|
System cleanliness |
Check periodically that the heat sinks are free from obstacles and dust. |
Once every 6 to 12 months |
System running status |
|
Once every six months |
Electrical connection |
|
The first inspection is 6 months after the initial commissioning. From then on, the interval can be 6 to 12 months. |
Grounding reliability |
Check that ground cables are securely connected. |
The first inspection is 6 months after the initial commissioning. From then on, the interval can be 6 to 12 months. |