Verifying the Installation
Verifying the Cabinet Installation
Check the cabinet installation against the items listed in Table 3-4. Take appropriate measures for the disqualified items immediately.
No. |
Check Item |
Check Result |
---|---|---|
1 |
Labels on the cabinet are clear and properly pasted. |
- |
2 |
Screws for securing the cabinet are properly installed. |
- |
3 |
The exhaust valve on the cabinet is tightened properly. |
- |
4 |
The entire water loop has no leakage or condensation after water is supplied. |
- |
5 |
Paint on the cabinet is not scraped or the surface is not stained. If not, apply paint or clean up the stains. |
- |
6 |
The instructions and accessories delivered with the equipment are intact. |
- |
Verifying the Chassis Installation
Verify the cabinet installation against the Table 3-5 checklist. Take appropriate measures for the disqualified items immediately.
No. |
Check Item |
Check Result |
---|---|---|
1 |
Labels on the chassis are clear and properly pasted. |
- |
2 |
Screws for securing the chassis are properly installed. |
- |
3 |
Paint on the chassis is not scraped or the surface is not stained. If not, apply paint or clean up the stains. |
- |
4 |
Filler panels are installed in all vacant slots. |
- |
5 |
The instructions and accessories delivered with the equipment are intact. |
- |
Verifying the Cable Installation
Check installation of cables against the items listed in Table 3-6. Take appropriate measures for the disqualified items immediately.
No. |
Check Item |
Check Result |
---|---|---|
1 |
Cables are properly routed in the cabinet, complying with Huawei's cable layout specification. |
- |
2 |
Power cables and PGND cables are properly connected. |
- |
3 |
PGND cables and power cables are in good condition without any splice. |
- |
4 |
The excessive parts of PGND cables and power cables are trimmed off. The cables cannot be coiled up. |
- |
5 |
Power cables, PGND cables, and signal cables are independently bundled. The pitches between power cables and signal cables as well as between PGND cables and signal cables meet the requirements. |
- |
6 |
Cables are not routed on the dissipation holes of devices. |
- |
7 |
Cables are bundled in uniform spacing with appropriate tightness. |
- |
8 |
The bending radius at the corner meets the specifications. |
- |
9 |
The installed cables do not block the indicators or hinder replacement of components. |
- |
10 |
Unused optical cable connectors are covered by protective caps. Unused optical modules are covered by dust covers. |
- |