If the cabinet is fully configured with 2288C V5 servers, the PDU provides two three-phase 380 V 32 A AC power supplies in star topology. The input power of each power supply is 19,200 W (200 W x 3 x 32), which meets requirements for the total power of 19.2 kW and N+N redundancy.
Figure 1-4 and
Figure 1-5 show the power distribution for the cabinet configured with an external CDU cabinet and a built-in CDU box.
Figure 1-4 Power distribution for the cabinet configured with an external CDU cabinet![]()
Figure 1-5 Power distribution for the cabinet configured with a built-in CDU box![]()
If the 2288C full liquid cooling cabinet is configured with a CDU box, it supports nineteen 2288C V5 servers.