No relevant resource is found in the selected language.
This site uses cookies. By continuing to browse the site you are agreeing to our use of cookies. Read our privacy policy>
Your browser version is too early. Some functions of the website may be unavailable. To obtain better user experience, upgrade the browser to the latest version.
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document.
Note: Even the most advanced machine translation cannot match the quality of professional translators.
Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Testing the PSU Redundancy
Testing the PSU Redundancy
Case No.
4.3.1
Objective
To check whether the PSUs on the server work in redundancy mode.
Test Networking
See the test networking diagram.
Prerequisites
The server is properly powered on.
A Linux OS has been installed on the server.
Procedure
Install four PSUs on the server and connect the power cables to the PSUs.
Power on the server and access the OS.
Remove the power cable from one of the PSUs.
Expected Result
After the PSU is removed, the server is still operating properly.