No relevant resource is found in the selected language.
This site uses cookies. By continuing to browse the site you are agreeing to our use of cookies. Read our privacy policy>
Your browser version is too early. Some functions of the website may be unavailable. To obtain better user experience, upgrade the browser to the latest version.
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document.
Note: Even the most advanced machine translation cannot match the quality of professional translators.
Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Checking the Server Installation
Checking the Server Installation
Case No.
4.1.3
Objective
To ensure that the server can be properly installed in a standard cabinet.
Test Networking
N/A
Prerequisites
The ambient temperature, altitude, and humidity in the equipment room meet the requirements. For details, see the server installation guide.
Procedure
Install guide rails.
Lift the server horizontally by at least two persons, place it on the guide rails, and push it into the cabinet.
Connect power cable from the server to the cabinet based on the power distribution requirements of the equipment room. Before connection, check whether the server is equipped with one PSU or two PSUs in 1+1 redundancy mode.
Expected Result
The server is properly installed in a standard cabinet.
The power distribution in the cabinet is appropriate.