Installing the Relay
Procedure
- Attach mounting ears and retention assemblies onto the ends of the rear panel, as shown in Figure 6-21.
- Orient the relay ports to the multi-functional conference table, and place the relay inside the center rack, as shown in Figure 6-23.
- Tighten one M6 x 16 hex socket screw at each end, as shown in Figure 6-22.