No relevant resource is found in the selected language.
Your browser version is too early. Some functions of the website may be unavailable. To obtain better user experience, upgrade the browser to the latest version.
Huawei uses machine translation combined with human proofreading to translate this document to different languages in order to help you better understand the content of this document.
Note: Even the most advanced machine translation cannot match the quality of professional translators.
Huawei shall not bear any responsibility for translation accuracy and it is recommended that you refer to the English document (a link for which has been provided).
Installing a UPS
Installing a UPS
Rack-Mounting a UPS
Reserve a space of 1 U between the UPS and batteries for routing battery power cables.
Reserve a space of 50 mm between the battery communications port and the cabinet for installing a communications cable.
Reserve a space of 44 mm between the battery edge and the rack edge for installing battery power cables.
In rack-mounted installation scenarios, the front panels of the UPS and lithium batteries are not on the same plane.
Install the mounting ears on both sides of the UPS.
Install the guide rails on the rack, and then install the UPSs and batteries with mounting ears on the rack.