Verifying the Installation
No. |
Item |
Expected Result |
---|---|---|
1 |
Cable routing |
Cables are routed properly according to engineering requirements. |
2 |
Cable connection |
All cables are connected securely and correctly, and they are free of damage. Bolts are tightened to specified torque using a torque wrench. |
3 |
Cable connection to USB, network, and other ports |
Signal cables to USB, network, and other ports are connected securely and correctly. |
4 |
Cable labels |
Labels are neatly attached to both ends of each cable, and the information on the labels is concise and legible. |
5 |
Ground cable connection |
The UPS ground cable is securely connected to the equipment room ground bar. Use a multimeter to measure the resistance between the UPS ground cable and the equipment room ground bar. The resistance is less than 0.1 ohm. |
6 |
Spacing between cable ties |
Distances between cable ties are the same, and no burr exists. |
7 |
Operating environment |
The inside and outside of the cabinet are free from conductive dust or other sundries. |