Installing a Drainage Pipe for the Smart Cooling Product
Context
The condensate drainpipe has been installed on the smart cooling product before delivery. You need to route the drainpipe from the bottom onsite.
Procedure
- Remove the baffle plate from the smart cooling product.Figure 4-10 Removing the baffle plate
- Use an electrician's knife to cut a cross in the middle of the rubber plug for the water pipe hole at the bottom of the cabinet.Figure 4-11 Cutting the rubber plug
- Route the drainpipe.Figure 4-12 Drainpipe routed from the bottom
- After routing the water pipe, secure it to the pipe assembly using cable ties, and seal the cable hole using firestop putty.
- After connecting the drainpipe, check whether the drainage is normal.
- Install the baffle plate for the smart cooling product.
Follow-up Procedure
Before removing the smart cooling product, remove the upper baffle plate and the side panels on both sides of the cabinet.