Application Description
Service Description
The hardware installation manual instructs you to install hardware equipment in an equipment room during site deployment. The hardware installation process is as follows:
1.Designing the equipment room layout: Huawei provides you with the design diagram of the equipment room for your reference.
2.Installing cabinets: Huawei provides you with two types of cabinets: N68E-22 and N68E-21-N.
Compared with N68E-22, N68E-21-N has better anti-earthquake performance. You can choose one as required.
3.Installing hardware inside a subrack, such as the boards, cables, fan subrack, EMU, and power supply module.
4.Commissioning equipment. Documentation Description
The following scenario-oriented base station controller hardware installation guides are provided for you to install hardware:
1.N68E-22 Cabinet Installation Guide and N68E-21-N Cabinet Installation Guide: provides guidance on equipment room layout and
cabinet installation.
2.XXXX Installation Guide and XXXX Quick Installation Guide: instructs you to install hardware in cabinets. If it is inconvenient
to carry a PC to the construction site, print XXXX Quick Installation Guide to guide your cabinet installation.
3.GPS Satellite Antenna System Quick Installation Guide: details the procedure for installing the Global Positioning System (GPS)
satellite antenna system, which needs to be performed before equipment commissioning.
4.XXXX Commissioning Guide: provides detailed information about equipment commissioning.
Huawei provides you with commissioning guides for the following products:
 Highlights
A quick installation guide uses figures and descriptions to illustrate how to install components in cabinets. In addition, printing
is supported. This way, you can carry the hard copies onsite for reference.
A quick installation guide uses figures and descriptions to illustrate how to install components in cabinets in a detailed and comprehensive way.
For example, precautions and indicator status during the installation are provided. Equipment room planning for cabinet installation in the initial phase of site deployment
Installation of components in cabinets
Reference Documents
Installation Guide
QuickInstallation Guide
N68E-22Cabinet Installation Guide
N68E-21-NCabinet Installation Guide
GPS Satellite Antenna Syste Quick Installation
This post was last edited by BenLiu at 2019-09-27 11:36. |